Subscribe Us

Ads Here

Wednesday, February 26, 2020

Report: LRT-2 to resume full operations by June, says LRTA

It’s been almost five months since the Light Rail Transit Line 2 (LRT-2) partially closed down due to the fire that broke out between the rail line’s Katipunan and Anonas stations. In its initial statement, the Light Rail Transit Authority (LRTA) said that repairs could take at least nine months.

So, more than halfway into that given period, how have the said repairs progressed so far? Well, here’s a bit of good news: the agency has promised that the LRT-2 will resume full operations by the end of June—that’s at least one week ahead of schedule.

According to an Inquirer.net report, LRTA spokesperson Hernando Cabrera recently told the House committee on transportation that the agency plans to speed up its procurement process so the LRT-2 may resume operations between Anonas and Santolan as early as possible. “We’re confident that by June, or even prior to June, we can complete the repairs and that the provisional operations will be implemented,” he said.

However, Cabrera added that while the trains may soon reach the line’s three easternmost stations, operations won’t normalize as quickly: “This means the trains may be a bit slower, or cannot run for too long at any given time, but [we] will at least restore the stations.”

The spokesperson also added that after the procurement process has been completed, the actual repairs may take only two to three months.

How have you coped with the partial shutdown of the LRT-2 in the last few months? Also, what can you say about these most recent developments?

[ArticleReco:{"articles":["34584","34603","34604","34661"], "widget":"See Also"}]


Source: Top Gear

No comments:

Post a Comment